What Is Integrated Project Delivery: The Contract (Part 1 of 3)

This is a 3 part series focusing on Integrated Project Delivery as a contract, a lean operating system and a culture.

Integrated Project Delivery (IPD) is gaining popularity among owners, contractors and design teams as a means to unlock creativity, drive reliability, and successfully deliver complex capital projects.

With all of the recent hype about the success of IPD and many large owners looking to pilot their first IPD projects, what exactly is Integrated Project Delivery?  This series will explore Integrated Project Delivery as a contract form, a lean operating system and as a transformational culture.

Integrated Project Delivery (IPD) is a delivery model for delivering construction projects using a single contract for design and construction with a shared risk/reward model, guaranteed costs, waivers of liability between team members, an operating system based on lean principles, and a collaborative culture.

It is often referred to as Lean Integrated Project Delivery or Lean IPD to show the strong tie between the contracting method and the implementation of lean principles in the management of the project.

Contract:

There are several multiparty agreements on the market right now.  For the purposes of this post, we will call the contract an IPD Agreement.

Integrated Project Delivery teams are contractually tied together differently than traditional design/bid/build, CM-at-risk, and Design/Build agreements.  The typical IPD agreement includes the primary design firm, the primary builder, and the owner in a single contract for a single dollar value.  The contract lays out the responsibilities of the designer, contractor and owner but also makes it clear that successful delivery of the project is the responsibility of all three.

Signatories: The contract is always signed by the owner, lead designer and lead builder.  Some owners choose to have more than 3 signatories to the agreement, bringing in other design and trade partners to be primary signatories.  If the other parties are not signatories, they are typically subcontracted under one of the primary signatories and language is incorporated into the subcontract to tie them to the terms of the master IPD agreement.  A later blog post will explore the pros and cons of tri party vs poly party agreements (more than 3 signatories).

Some of the designers and subcontractors will agree to put their profit at risk alongside the primary designer and builder.  For this post we will call firms risk/reward partners if they put their profit at risk. 

Other trades and consultants will be brought into the agreement with traditional subcontract structures on either a lump sum or time and material basis.  They can be negotiated or traditionally bid, typically once the design is significantly complete.

Risk/Reward Parties: IPD contracts have a shared risk/reward component based on the financial outcome of the project.  The signatories and other risk/reward partners agree to put their profit at risk in exchange for a guarantee of their costs and shared savings if the project performs well.  These firms agree to be reimbursed on a transparent cost plus overhead and profit basis.

For design firms, their billing rates are separated out into a direct cost component, an overhead component and a profit component.  This is often calculated as a multiple of direct labor cost.

For construction firms, all labor, material and subcontracts are billed at direct cost plus an overhead percentage and profit.

For any party participating in the risk/reward pool, the rates and overhead are subject to an audit by an independent audit firm.  While the audit may not take place on smaller projects, it is highly likely on larger contracts and can be a time consuming process.

Contract Amount: The contract is typically structured with costs for design, construction and a shared contingency for the team.  All of the risk/reward parties have their profit fixed as a lump sum amount at the time the contract amount is negotiated and agreed to by the team.

Risk / Reward Plan: The contract will lay out the terms by which the risk/reward parties can lose some or all of their profit if the project does not meet its budget and schedule goals.  If all profit is lost, the owner typically agrees to pay for the project at cost (including overhead although this may be capped), thus allowing the team members not to profit on the project but also not to lose money.  There is a massive opportunity cost for firms to deliver a large project and only recover their costs.

If the project is delivered below its financial targets, the team will get all of their fixed profit and share in the savings of the project, thus improving their profit.  A negotiated percentage of the savings goes back to the owner and the rest is split between the risk/reward partners.

Leadership Team: The contract defines a leadership team that is responsible for delivering the project on time, on budget and at the quality requested by the owner.  Some agreements call this the Core Group or the Project Management Team (PMT) and there are surely other names. The important concept is that the project is jointly managed by a representative from the owner, architect and contractor.  Others may be added to this leadership team such as a user representative (client) or other representatives from the risk/reward partners.

The primary goal of this contract model is to remove barriers to collaboration and innovation while aligning incentives for the project team.

The contract structure allows scope to transfer between firms based on who can most cost-effectively deliver the work.  Design and trade partners can work together without traditional silos.  Firms know that they will not lose money on the project and back charges among risk/reward partners are eliminated.

Through the IPD agreement, the major parties are contractually aligned to “sink or swim together.”  Success is based on the overall financial and schedule outcomes of the whole design and construction team instead of individual successes or failures.  While the IPD agreement is a major deviation and improvement from typical contracting structures, it is only part of Integrated Project Delivery.

Looking to Learn More about IPD? Check out these Online Courses and Certificates.

See part 2, Lean Operating System
This post was originally published on the Lean Construction Blog.

+ posts

James is an expert in the set-up and structure of large, complex capital projects using Lean and Integrated Project Delivery to drive highly reliable results.

He has negotiated IPD contracts and delivered over $650M in complex healthcare projects as an Owner's Representative with multiparty contracts, aligned team incentives and collaborative delivery models.

Scroll to Top